Library Renovation Project
June 27, 2006
Library Renovation Update
- General Information
- Contractor has 30 days (end of June) to submit complete schedule for Review.
- University and Contractor has 90 days (end of August) to work out all the details and finalize the schedule
- Contractor will give us a 2 week look ahead at each meeting
- We will send e-mails as necessary
- TimeLines
- Academic Services due to complete April 07
- Library due to complete November 07
AS Bldg
Item |
Status |
Complete |
| Demo 2nd & 3rd Floor |
Current - final week |
Est July 1 |
| Elevator on North Side |
Schedule in process |
Est Dec 06 |
| Ear Plugs available |
Current |
|
| Concrete Coring - AS 120 ceiling |
Scheduled July 3 |
One Day |
| Interior Stairwells - demo, rehab |
Current |
Est July 10 |
Library
Item |
Status |
Complete |
| Lower Level -demo |
Begin 7/6 |
8 days |
| 1st Floor demo |
Begin 7/13 |
8 days |
FUTURE CONSIDERATIONS
All power to both buildings will be shut down for a 12 hour period to make change over to new power systems.
Each building will be done separately
POSSIBLE DATES:
Aug 26 (Saturday)
Sept 9 (Saturday)
Sept 16 (Saturday)
Working with Library to determine best dates for them.
Do you have any problems with these dates in the AS Side? Please notify me immediately.
No meeting next week.
June 20, 2006
Library Renovation Update
- General Information
- Contractor has 30 days (end of June) to submit complete schedule for Review.
- University and Contractor has 90 days (end of August) to work out all the details and finalize the schedule
- Contractor will give us a 2 week look ahead at each meeting
- We will send e-mails as necessary
- TimeLines
- Academic Services due to complete April 07
- Library due to complete November 07
- Current Events(changes in bold)
- Demo on 2nd and 3rd Floor of Academic Services building currently underway - Estimated completion week of June 26
- Trash chute has been constructed on north side of building
- Trash chute will be constructed on south side of building -Being constructed 6/20/06
- Demo work hours increased to meet deadlines
- Excavation for elevators will not begin until all materials are out of 2nd and 3rd floors Estimate around July 15
- Bead blasting to remove mastic from floors on 2nd floor in process expect to finish by Friday June 16-2nd floor done
- All utilities connections have been secured - electrical, hvac and water
- Abatement of 2nd and 3rd will occur concurrently
- Abatement continuing - estimated completion week of July 3
- Elevator tower on AS side
- Current fencing in this area - 180 days - (through December)
- Beach Hut
- Temporary entrance into Beach - under construction
- NEW ITEMS
- Will begin layout of ceilings and walls on 2nd and 3rd week of June 26
- Ear plugs will be available to staff on 1st floor of AS building
- Ear plugs for staff, students, library clients will be available through the library
- Library PA system has been isolated - no PA in AS building
- Ceiling work in AS 120 deferred until Aug 21
Other considerations
- Sidewalk Replacement near construction site -
- Education Bldgs - project has begun
- Vacate LAC and Academic Advising
Library
- Current events
- Barrier walls are under construction on lower level, 1st floor, in stairwells, etc.
- Elevator issue has been resolved
- First phase (lower and 1st) estimated to be approximately 7 - 8 months. (Feb-March 07)
- Should begin demo in Library week of June 19th
- Will begin utilities work week of June 26
- Elevator tower next to MM building
- Are removing landscape and hardscape next to MM 100 within the week.
AS 120
- Demo of ceiling/ceiling tile in AS120
- Due to begin around July 1- see above - this has been delayed until Aug 21
- Demo takes one week-
- HVAC reinstall takes 3 weeks
- Area includes all of Center for Community Engagement and part of ED PAC
- Resolve plan in the works with affected tenants.
June 11, 2006
Library Renovation Update
- General Information
- Contractor has 30 days (end of June) to submit complete schedule for review.
- University and Contractor has 90 days (end of August) to work out all the details and finalize the schedule
- Contractor will give us a two-week forecast at each meeting with the CSULB Project Management Team.
- Some building materials will be delivered using the fire lane traveling west from East Campus Drive, past PH1, then south on the walkway from F03 to the Beach Hut. Please watch for vehicles.
- Because parking is being lost during the construction, the Anatol Center is not to be scheduled for any activities to which campus visitors are invited
- Timelines
- Academic Services due to complete April 07
- Library due to complete November 07
- Current Events
- Demo on 2nd and 3rd Floor of Academic Services building currently underway
- Trash chute has been constructed on north side of building
- Trash chute will be constructed on south side of building
- Excavation for elevators will not begin until all materials are out of 2nd and 3rd floors
- Bead blasting to remove mastic from floors on 2nd floor in process expect to finish by Friday June 16
- All utilities connections have been secured - electrical, HVAC and water
- Abatement of 2nd and 3rd will occur concurrently
- Work plan being submitted today
- Elevator tower on AS side
- Current fencing in this area - 180 days - (through December)
- Beach Hut
- Temporary entrance into Beach Hut will be through the north double doors of Academic Advising
- Current events
- Barrier walls are under construction on lower level, 1st floor, in stairwells, etc.
- Elevator staging issue has been resolved, eliminating failure of cars to arrive on the 1st floor.
- First phase (lower level and 1st floor) estimated to be approximately 7 - 8 months. (Feb-March 07)
- Demolition work in the Library scheduled to begin week of June 19th
- Elevator tower next to MM building
- Are removing landscape and hardscape next to MM 100 within the week.
- Will not excavate for the new elevator tower until 3rd floor AS demolition is complete.
Other considerations
- Sidewalk Replacement near construction site -
- Education Bldgs - begins June 19th through July 10th
- Relocation of the Learning Assistance Center and Academic Advising should be complete by Aug 1st.
- Vacate LAC and Academic Advising
- AS 120
- Demo of ceiling/ceiling tile scheduled to begin around July 1 and last approximately one week.
- HVAC reinstall will take approximately 3 weeks
- Area includes all of Center for Community Engagement
- Contractor will remove furniture
June 6, 2006
Library Renovation Update
- Today was first meeting with contractor, architect, CSULB Project Management Team.
- General Information
- Contractor has 30 days (end of June) to submit complete schedule for Review.
- University and Contractor has 90 days (end of August) to work out all the details and finalize the schedule
- Contractor will provide a 2 week forecast at each meeting
- Timelines
- Academic Services due to complete April 07
- Library due to complete November 07
- Current Events
- Demo on 2nd floor of AS Building
- Lighting and carpet are out
- Demo on 3rd floor of AS Building
- Developing plan of execution - how to get the material out of the building
- Electrical and HVAC Sub contractors are doing exploratory work to determine feed sites for future disconnection/reconnection
- Electrical Closets, ceilings, plumbing
- Elevator tower on AS side
- Removing and reutilizing brick
- Digging in this space in approx 10 - 12 days
- Current fencing in this area - 180 days - (through December)
- Beach Hut
- Temporary entrance into Beach Hut will be through the north double doors of Academic Advising
- Plant Operations will build a vestibule inside to protect Academic Advising.
- Once fencing is down (see above), Beach Hut Services will be returned to exterior entrance
- Library
- Current events
- Barrier walls are under construction on lower level, 1st floor, in stairwells, etc.
- First phase (lower and 1st) estimated to be approximately 7 - 8 months. (Feb-March 07)
- Should begin demo in Library late next week.
- Elevator tower next to MM building
- Will begin removing landscape and hardscape next to MM 100 within the week.
- Will not excavate until 3rd floor AS demo is complete
|